CENTRIFUGAL
PUMP TEST RIG
OBJECTIVE:
APPARATUS:
SUGGESTED EXPERIMENTAL PROCEDURE:
Step2: Priming the pump-set before starting. Priming
means taking the air present in the suction and pressure pipes, volute casing
by filling them with water. Ensure to close the aircock / priming adaptor as
the air bubbles cease appearing and continous stream of water comes from
aircock/ priming adaptor.
NOTE: In the supplied
apparatus, a self- priming pump is used so the pump does not require priming.
Step3: The
speed control on the motor is set to a value and at the same time the flow
control valve was adjusted to give the maximum possible discharge.
Step4:
Conditions were allowed to steady before the rate of discharge Q, suction head,
discharge head, load on the motor and r.p.s. value were recorded.
Step5: The
flow-rate is reduced in stages and the above procedure is repeated.
SAMPLE DATA SHEET:
Arm
distance, m =
rg = 9810
Area
of collecting tank, a, m2 =
Run No |
Discharge measurement |
Pump Speed (r.p.s) |
Suct-ion Head (m) |
Delivery head (m) |
Total head (m) |
Load (N) |
Torque Nm |
Water power |
Input power P (w) |
Effi- ciency h (%) |
|||
|
Initial h1 (m) |
Final h2 (m) |
Time (sec) |
Discharge Q= (m3/ sec) |
|||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|